Timber Bridge Demolition at Ipswich Nature Centre

Timber Bridge Demolition at Ipswich Nature Centre

Project summary: Total Demolition Brisbane removed approximately 150 lineal metres of timber bridges and walkways, including their supporting posts and footings, at Ipswich Nature Centre for HNG Contractors. Using our own crew, excavators and skip trucks, the project was completed in approximately one week in April 2026 and handed over on the builder’s agreed date.

Total Demolition Brisbane 3-tonne Cat excavator lifting a section of timber bridge decking at Ipswich Nature Centre
The compact 3-tonne excavator lifting cut decking sections at the work face.

Project at a Glance

LocationIpswich Nature Centre, Queens Park, Ipswich
ClientHNG Contractors (builder)
CompletedApril 2026
DurationApproximately one week
ScopeApproximately 150 lineal metres of timber bridges and walkways, including posts and footings
CrewFour Total employees: two operators and two truck drivers, who also carried out the timber dismantling
EquipmentTotal-owned 3-tonne and 11-tonne excavators, skip trucks and dismantling equipment
AccessVia Burley Griffin Drive; restricted access within the work site
Site settingNature Centre remained open to visitors; work area fenced off
Waste disposalLandfill at BMI, Stapylton
HandoverStructures removed, area levelled, agreed deadline met

The Brief: Clear the Existing Timber Structures

HNG Contractors engaged Total Demolition Brisbane to remove the existing timber bridges and walkways at Ipswich Nature Centre ahead of further building works. The removal went beyond the decking and handrails: the supporting posts and footings had to come out as well, leaving the area clear for the builder’s next stage.

The project covered an estimated 150 lineal metres of structures. Access was via Burley Griffin Drive, and space within the removal area itself was restricted, so the dismantled material had to be carried out by smaller machinery to a larger loading area.

Timber walkway and bridge at Ipswich Nature Centre before demolition, with orange safety fencing in place
One of the timber walkways before removal, fenced off from the open Nature Centre.

Planning Around Access, Trees and Underground Services

The Nature Centre stayed open to the public for the whole project. Temporary fencing separated the work site from the surrounding grounds so visitors could keep using the rest of the centre while the crew worked.

Before we started, the builder identified the established trees and the underground services in and around the work area. Our team planned the removal sequence and machinery movements around them, so nothing outside the scope was disturbed.

Tight access shaped the equipment selection and the loading process. A compact 3-tonne excavator worked within the restricted area, while an 11-tonne excavator operated at a larger laydown area where waste could be loaded into skip bins.

Total Demolition Brisbane operator standing beside a large protected fig tree at Ipswich Nature Centre
Established trees were identified and protected throughout the removal.
Compact excavator working carefully beside an electrical services cabinet at Ipswich Nature Centre
Working around the services the builder had identified before we started.

Combining Manual Dismantling With Mechanical Removal

The crew first used chainsaws to cut the timber structures into manageable sections. The 3-tonne excavator then lifted the sections out and removed the remaining components, including the posts and footings.

The same compact excavator carried the removed pieces along the available access route to the laydown area. There, the 11-tonne excavator picked up the material and placed it into skip bins for transport off site. This staged approach let the team remove complete structures despite the limited space at the work face.

Total Demolition Brisbane operator walking beside a Cat excavator in the restricted-access work area at Ipswich Nature Centre
Tight access between trees and garden beds shaped the machinery choice.
11-tonne Cat excavator loading demolition timber at the Ipswich Nature Centre laydown area
The 11-tonne excavator loading timber into skip bins at the laydown area.

An In-House Crew and Equipment Fleet

Four Total employees delivered the project: two operators and two truck drivers. The same crew carried out the chainsaw dismantling, coordinating the cutting, excavation, material movement and waste removal stages between them.

The excavators, skip trucks and dismantling equipment were all owned by Total. Having the crew and the equipment under one roof meant we controlled the removal and loading sequence from the first cut through to final handover, with no waiting on hired plant or subcontractors.

Total Demolition Brisbane crew member with a cage trailer and excavator loading timber waste at Ipswich Nature Centre
Two operators and two truck drivers delivered the whole job.

Waste Removal and a Levelled Finish

The removed timber and footing material were transported in our own skip trucks to BMI at Stapylton for landfill disposal. Once the structures were out, the team levelled the work area ready for handover to HNG Contractors.

Total Demolition skip bin and ute at the Ipswich Nature Centre site for timber and footing waste
Our own skip trucks took the timber and footing material to BMI at Stapylton.
Levelled ground at Ipswich Nature Centre after the timber bridges and walkways were removed
Levelled and ready for handover to HNG Contractors.

Delivered Within the Builder’s Timeframe

Completed in April 2026, the work took approximately one week and met the builder’s agreed deadline. HNG Contractors was happy to have the area handed back on time.

The project shows what our team does well: combining manual dismantling, compact excavation and larger loading equipment on a site with restricted access, while working around identified trees and underground services and keeping a public facility open throughout.

Planning Bridge, Walkway or Structural Demolition?

Total Demolition Brisbane takes on commercial demolition and site clearance for builders and councils across Brisbane, Ipswich and Logan, from timber and steel structures to full house demolitions. Our own excavators, skip trucks and operators mean we can quote a program and hold to it. Call us on (07) 3012 6702 or request a quote to discuss your site access, removal scope and timeframe.

FAQs

Can you demolish structures in a park or public facility that stays open?

Yes. At Ipswich Nature Centre the facility remained open for the whole week. The work area was fenced off, machinery movements were planned around visitor areas, and the site was handed back levelled and clear.

How do you handle demolition where access is restricted?

We match the machine to the space. A compact 3-tonne excavator works at the face, carrying material along the available route to a laydown area where a larger excavator loads skip bins. Manual cutting with chainsaws reduces sections to a size the small machine can lift.

Do you remove posts and footings as well as the decking?

Yes. The scope at Ipswich included the supporting posts and footings, not just the walkway surfaces, so the builder received a clear, levelled area.

Do you work in Ipswich?

Yes. Ipswich, Springfield and the western corridor are part of our regular service area, alongside Brisbane and Logan.